- 25-04-24Periodic maintenance cooling system BIT-2BCD
- 22-04-24Periodic maintenance cooling system BIT-2A
- 18-04-24Maintenance diesel tanks power generators BIT-2A
- 15-04-24Periodic maintenance cooling system BIT-1
- 11-04-24Maintenance computair units BIT-2A
- 09-04-24Maintenance computair units BIT-2C
- 08-04-24Maintenance computair units BIT-2B
- 05-04-24Firewall Maintenance
- 04-04-24Periodic maintenance fire detection and suppression systems BIT-2A and BIT-2BCD
- 04-04-24Maintenance diesel tanks power generators BIT-2A
Emergency maintenance B side UPS of BIT-2B
19-12-2018 00:00:00
- 19-12-2018 07:00:00
Urgency: Emergency
Affected services: customers with equipment in BIT-2B
Expected Impact: possible loss of power redundancy
Customer intervention required: no
Referencenumber: 159517
Summary:
On Wednesday the 19th of December between 0.00 and 7.00h our UPS-set supplier will be performing emergency maintenance on our B side UPS in BIT-2B.
During this maintenance the B side UPS will be put in bypass mode. We do not expect any disruption in the power supply, but it is possible that the ATS in your rack (if applicable) will switch to the other power feed. If you have received warnings from BIT that your total power consumption is close to the limit, we recommend that you take action before this maintenance starts.
In case of disruption of one of the power feeds, which we do not expect, the other feed will be available as normal. We do recommend that you check if your equipment is connected to both power feeds.
Details:
During the maintenance our supplier will replace some of the communication hardware of de B side UPS.
Affected services: customers with equipment in BIT-2B
Expected Impact: possible loss of power redundancy
Customer intervention required: no
Referencenumber: 159517
Summary:
On Wednesday the 19th of December between 0.00 and 7.00h our UPS-set supplier will be performing emergency maintenance on our B side UPS in BIT-2B.
During this maintenance the B side UPS will be put in bypass mode. We do not expect any disruption in the power supply, but it is possible that the ATS in your rack (if applicable) will switch to the other power feed. If you have received warnings from BIT that your total power consumption is close to the limit, we recommend that you take action before this maintenance starts.
In case of disruption of one of the power feeds, which we do not expect, the other feed will be available as normal. We do recommend that you check if your equipment is connected to both power feeds.
Details:
During the maintenance our supplier will replace some of the communication hardware of de B side UPS.