- 21-12-23Maintenance fire suppression BIT
- 13-12-23Fiber maintenance BIT-1 - Equinix AM7
- 12-12-23Black building emergency power test BIT-2
- 06-12-23Certification fire alarm and gas extinguishing system BIT-1, BIT-2A and BIT-2BCD
- 05-12-23Black building emergency power test BIT-1
- 10-11-23Maintenance fire detection and suppression systems BIT-1, BIT-2A and BIT-2BCD
- 26-10-23Maintenance management software virtualisation platform
- 24-10-23Periodic maintenance cooling system BIT-2BCD
- 23-10-23Periodic maintenance cooling system BIT-2A
- 19-10-23Emergency maintenance MySQL servers and network stats server
Periodic maintenance cooling system BIT-1
16-10-2023 08:00:00
- 25-10-2023 17:30:00
Urgency: Planned
Affected services:
- Colocation in BIT-1
Expected impact: Slight increase in temperature
Customer intervention required: No
Reference number: 187644
Summary:
Periodic maintenance is performed on the cooling system in BIT-1.
Details:
The downflow units (responsible for blowing cold air in the data centers) will be shut down for maintenance one at a time. This may result in a slight temporary increase in temperature in specific parts of the data center.
The maintenance will take place every workday between 08:00 and 17:30 hrs
This maintenance will be supervised by BIT engineers who will monitor the temperature in the data center closely.
Affected services:
- Colocation in BIT-1
Expected impact: Slight increase in temperature
Customer intervention required: No
Reference number: 187644
Summary:
Periodic maintenance is performed on the cooling system in BIT-1.
Details:
The downflow units (responsible for blowing cold air in the data centers) will be shut down for maintenance one at a time. This may result in a slight temporary increase in temperature in specific parts of the data center.
The maintenance will take place every workday between 08:00 and 17:30 hrs
This maintenance will be supervised by BIT engineers who will monitor the temperature in the data center closely.