- 31-05-24Maintenance UPS sets BIT-2B
- 30-05-24Maintenance UPS sets BIT-2D
- 29-05-24Maintenance UPS-sets BIT-2C
- 28-05-24Maintenance UPS sets BIT-1
- 22-05-24Maintenance UPS sets BIT-2A
- 16-05-24Periodic maintenance powerinfra and transformers BIT-2
- 25-04-24Periodic maintenance cooling system BIT-2BCD
- 22-04-24Periodic maintenance cooling system BIT-2A
- 18-04-24Maintenance diesel tanks power generators BIT-2A
- 15-04-24Periodic maintenance cooling system BIT-1
Maintenance power generators BIT-2A
25-02-2019 08:00:00
- 25-02-2019 17:00:00
Urgency: planned
Affected services: equipment in BIT-2A
Expected Impact: no redundancy power generators
Customer intervention required: no
Referencenumber: 159750
Summary:
In response to the maintenance on the power generators on the 21st of January 2019 some parts will be replaced preventively.
Details:
During this maintenance, one power generator instead of two will be available at all times. In case of a utility power failure, this generator will provide enough power for BIT-2A.
Affected services: equipment in BIT-2A
Expected Impact: no redundancy power generators
Customer intervention required: no
Referencenumber: 159750
Summary:
In response to the maintenance on the power generators on the 21st of January 2019 some parts will be replaced preventively.
Details:
During this maintenance, one power generator instead of two will be available at all times. In case of a utility power failure, this generator will provide enough power for BIT-2A.