- 01-04-25BIT as a Service
- 26-03-25Internetproviders verliezen rechtszaak over blokkeren websites
- 19-02-25BIT introduceert server-side e-mailfiltering met Sieve
- 06-02-25Shared hosting wordt opgefrist
- 28-11-24ECOFED uitgeroepen tot publieksfavoriet bij Computable Awards
- 21-11-24Een goede cloud heeft een kundige dirigent nodig
- 17-10-24ECOFED wint ICT Innovatieprijs Regio Foodvalley 2024
- 01-08-24BIT geeft kaarten weg voor F1 in Zandvoort
- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
Periodic maintenance power distribution BIT-2BCD
19-05-2020 00:00:00
- 19-05-2020 07:00:00
Urgency: Planned
Affected services:
- Feed A BIT-2B
- Feed A BIT-2C
- Feed A BIT-2D
Expected impact: None
Customer intervention required: No
Reference number: 167812
Summary:
Periodic maintenance will be carried out on the power distribution of BIT-2BCD.
Details:
Periodic maintenance will be carried out and a thermographic inspection will be conducted on the power distribution panel of BIT-2BCD. During this maintenance all main power switches will be serviced, therefore the UPS systems will be put in bypass mode one at a time.
We do not expect interruption of power to the UPS systems during this maintenance. In the unlikely event of interruption, the remaining feed is able to power all the systems. There will always be one feed fully operational. We strongly advice you to make sure all equipment is connected to both power feeds.
This entire maintenance will be supervised by BIT engineers.
Affected services:
- Feed A BIT-2B
- Feed A BIT-2C
- Feed A BIT-2D
Expected impact: None
Customer intervention required: No
Reference number: 167812
Summary:
Periodic maintenance will be carried out on the power distribution of BIT-2BCD.
Details:
Periodic maintenance will be carried out and a thermographic inspection will be conducted on the power distribution panel of BIT-2BCD. During this maintenance all main power switches will be serviced, therefore the UPS systems will be put in bypass mode one at a time.
We do not expect interruption of power to the UPS systems during this maintenance. In the unlikely event of interruption, the remaining feed is able to power all the systems. There will always be one feed fully operational. We strongly advice you to make sure all equipment is connected to both power feeds.
This entire maintenance will be supervised by BIT engineers.