- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
- 10-01-24BIT en partners zetten de koers voor een gedecentraliseerde Europese cloud met ECOFED-project
- 02-01-24Onze eigen stroom inkopen: de resultaten van 2023
- 24-11-23BIT Friday 2023
Preventive Maintenance UPS sets BIT-1
25-09-2020 00:00:00
- 25-09-2020 07:00:00
Urgency: Planned
Time window:
- 24/09/2020 00:00 hrs - 24/09/2020 07:00 hrs
- 25/09/2020 00:00 hrs - 25/09/2020 07:00 hrs
Expected impact:
- Possible loss of power redundancy
Customer intervention required: Yes
Reference number: 170303
Summary:
In cooperation with our supplier we will make improvements to the electrical installation. These improvements are the result of an inspection of the fire safety of the electrical installation (Scope 10 inspection).
Details:
During this maintenance, the UPS sets will be put in bypass mode one by one. We do not expect any disruption in the power supply, but it is possible that the central ATS in BIT-1 will switch to the other power feed. If you have received warnings from BIT that your total
power consumption is close to the limit, we recommend that you take action before this maintenance starts.
In case of an interruption of one of the power feeds, which might be possible during the maintenance, the other feed will be available as normal. We do recommend that you check if your equipment is connected to both power feeds.
Time window:
- 24/09/2020 00:00 hrs - 24/09/2020 07:00 hrs
- 25/09/2020 00:00 hrs - 25/09/2020 07:00 hrs
Expected impact:
- Possible loss of power redundancy
Customer intervention required: Yes
Reference number: 170303
Summary:
In cooperation with our supplier we will make improvements to the electrical installation. These improvements are the result of an inspection of the fire safety of the electrical installation (Scope 10 inspection).
Details:
During this maintenance, the UPS sets will be put in bypass mode one by one. We do not expect any disruption in the power supply, but it is possible that the central ATS in BIT-1 will switch to the other power feed. If you have received warnings from BIT that your total
power consumption is close to the limit, we recommend that you take action before this maintenance starts.
In case of an interruption of one of the power feeds, which might be possible during the maintenance, the other feed will be available as normal. We do recommend that you check if your equipment is connected to both power feeds.