- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
- 10-01-24BIT en partners zetten de koers voor een gedecentraliseerde Europese cloud met ECOFED-project
- 02-01-24Onze eigen stroom inkopen: de resultaten van 2023
- 24-11-23BIT Friday 2023
- 30-08-23A BIT of support: Hulp aan FCBU tijdens de oorlog in Oekraïne
Black building emergency power test BIT-1
07-12-2021 05:00:00
- 07-12-2021 07:00:00
Urgency: Planned
Affected services: Colocatie BIT-1
Impact: Main power grid BIT-1
Customer intervention required: No
Reference number: 175620
Summary:
On Tuesday, December 7th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-1.
Details:
During this maintenance, we will switch off the main power grid for the entire location BIT-1 for 60 minutes, in order to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.
Affected services: Colocatie BIT-1
Impact: Main power grid BIT-1
Customer intervention required: No
Reference number: 175620
Summary:
On Tuesday, December 7th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-1.
Details:
During this maintenance, we will switch off the main power grid for the entire location BIT-1 for 60 minutes, in order to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.