- 01-04-25BIT as a Service
- 26-03-25Internetproviders verliezen rechtszaak over blokkeren websites
- 19-02-25BIT introduceert server-side e-mailfiltering met Sieve
- 06-02-25Shared hosting wordt opgefrist
- 28-11-24ECOFED uitgeroepen tot publieksfavoriet bij Computable Awards
- 21-11-24Een goede cloud heeft een kundige dirigent nodig
- 17-10-24ECOFED wint ICT Innovatieprijs Regio Foodvalley 2024
- 01-08-24BIT geeft kaarten weg voor F1 in Zandvoort
- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
Maintenance power supply cooling BIT-2A
06-04-2022 07:00:00
- 06-04-2022 16:00:00
Urgency: Planned
Affected services:
- Cooling BIT-2A
Expected impact:
- Slight temperature increase locally in BIT-2A
Customer intervention required: No
Reference number: 178902
Summary:
Our supplier is going to perform maintenance on the switch that provides our office and part of the cooling in BIT-2A with generator power if needed.
Details:
In some cases the switch does not communicate correctly with the controller. To fix this, maintenance will be performed. During this maintenance, the switch will not be operable and therefore will not be able to switch to generator power in the event of a power outage. In that event, one third of the cooling in BIT-2A will be covered by the remaining cooling, the other equipment in BIT-2A will not be affected.
Affected services:
- Cooling BIT-2A
Expected impact:
- Slight temperature increase locally in BIT-2A
Customer intervention required: No
Reference number: 178902
Summary:
Our supplier is going to perform maintenance on the switch that provides our office and part of the cooling in BIT-2A with generator power if needed.
Details:
In some cases the switch does not communicate correctly with the controller. To fix this, maintenance will be performed. During this maintenance, the switch will not be operable and therefore will not be able to switch to generator power in the event of a power outage. In that event, one third of the cooling in BIT-2A will be covered by the remaining cooling, the other equipment in BIT-2A will not be affected.