- 30-12-22Wijziging stroomtarieven en portal updates
- 25-11-22BIT Friday
- 21-09-22BIT levert restwarmte aan Warmtebedrijf Ede
- 14-09-22Ruim helft organisaties kijkt naar duurzaamheid in keuze voor datacenter of cloudprovider
- 17-08-22Grand Prix Radio kiest voor betrouwbare hosting van radio-automatisering bij datacenter BIT
- 10-08-22Helft IT-beslissers gaat bij keuze voor nieuwe cloudleverancier voor grote naam
- 21-07-22Ruim een derde van IT-beslissers wil overstap maken naar Europees cloudplatform
- 30-06-22Eén op de vijf IT-beslissers heeft weinig vertrouwen in databescherming en privacy in de cloud
- 27-05-22Update RFO netwerk incident 17-04-2022
- 23-05-22Freedom of Information Coalition (FOIC) stapt naar de Europese rechter
Black building emergency power test BIT-2
13-12-2022 05:00:00
- 13-12-2022 07:00:00
Urgency: Planned
Affected services: Colocation BIT-2A and BIT-2BCD
Impact: Main power grid BIT-2A and BIT-2BCD
Customer intervention required: No
Reference number: 182575
Summary:
On Tuesday, December 13th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-2.
Details:
During this maintenance, we will switch off the main power supply for the entire location BIT-2 for 60 minutes to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.
Affected services: Colocation BIT-2A and BIT-2BCD
Impact: Main power grid BIT-2A and BIT-2BCD
Customer intervention required: No
Reference number: 182575
Summary:
On Tuesday, December 13th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-2.
Details:
During this maintenance, we will switch off the main power supply for the entire location BIT-2 for 60 minutes to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.