- 07-10-24Certification fire alarm and gas extinguishing system BIT-1, BIT-2A and BIT-2BCD
- 07-10-24Maintenance power generators BIT-2A
- 26-09-24Periodic maintenance fire detection and suppression systems BIT-2A and BIT-2BCD
- 25-09-24Maintenance statistics in the BIT portal
- 09-09-24Periodic maintenance power distribution BIT-2BCD
- 14-08-24Maintenance fire suppression BIT-2BCD
- 01-08-24Periodic maintenance fire detection and suppression system BIT-1
- 17-07-24Moving core network equipment in BIT-1
- 16-07-24Moving core network equipment in BIT-1
- 03-07-24Maintenance Microsoft SQL instances servers
Black building emergency power test BIT-1
06-06-2023 05:00:00
- 06-06-2023 07:00:00
Urgency: Planned
Affected services: Colocatie BIT-1
Impact: Main power grid BIT-1
Customer intervention required: No
Reference number: 183623
Summary:
On Tuesday, June 6th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-1.
Details:
During this maintenance, we will switch off the main power grid for the entire location BIT-1 for 60 minutes, in order to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.
Affected services: Colocatie BIT-1
Impact: Main power grid BIT-1
Customer intervention required: No
Reference number: 183623
Summary:
On Tuesday, June 6th between 5:00 hrs and 7:00 hrs we will perform a black building emergency power test at BIT-1.
Details:
During this maintenance, we will switch off the main power grid for the entire location BIT-1 for 60 minutes, in order to test our emergency power systems. During this test, engineers of BIT will be monitoring the situation on multiple locations and will, if the need should arise, intervene. We will perform a deep battery discharge test in the days leading up to the black building test. This is done because we will also run on battery before running on power generators. This discharge test will be performed on both feeds separately.