- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
- 10-01-24BIT en partners zetten de koers voor een gedecentraliseerde Europese cloud met ECOFED-project
- 02-01-24Onze eigen stroom inkopen: de resultaten van 2023
- 24-11-23BIT Friday 2023
- 30-08-23A BIT of support: Hulp aan FCBU tijdens de oorlog in Oekraïne
Maintenance UPS sets BIT-2D
30-05-2023 07:00:00
- 01-06-2023 17:30:00
Urgency: Planned
Affected services: Equipment in BIT-2D
Expected impact: Geen
Customer intervention required: No
Reference number: 183938
Summary:
From Tuesday 30 May to Thursday 1 June, our supplier will perform maintenance on the UPS sets in BIT-2D between 07:00 and 17:30. During the maintenance, the batteries of the A-feed will be partially replaced, while the B-feed will be completely replaced.
Details:
During the maintenance, 25% of the batteries will be disconnected at a time. The UPS sets are designed in a modular way, so 75% of the battery capacity for each feed will still be available. This capacity is sufficient to handle a power outage from the grid for approximately 20 minutes. The replacement process will start with the entire B-feed being replaced step by step, followed by a gradual replacement of a portion of the A-feed.
In the unlikely event that the feed of a particular UPS set is interrupted during the maintenance, the other feed will remain operational. We strongly advise you to double-check if all your equipment is connected to both feeds.
Affected services: Equipment in BIT-2D
Expected impact: Geen
Customer intervention required: No
Reference number: 183938
Summary:
From Tuesday 30 May to Thursday 1 June, our supplier will perform maintenance on the UPS sets in BIT-2D between 07:00 and 17:30. During the maintenance, the batteries of the A-feed will be partially replaced, while the B-feed will be completely replaced.
Details:
During the maintenance, 25% of the batteries will be disconnected at a time. The UPS sets are designed in a modular way, so 75% of the battery capacity for each feed will still be available. This capacity is sufficient to handle a power outage from the grid for approximately 20 minutes. The replacement process will start with the entire B-feed being replaced step by step, followed by a gradual replacement of a portion of the A-feed.
In the unlikely event that the feed of a particular UPS set is interrupted during the maintenance, the other feed will remain operational. We strongly advise you to double-check if all your equipment is connected to both feeds.