- 31-05-24Maintenance UPS sets BIT-2B
- 30-05-24Maintenance UPS sets BIT-2D
- 29-05-24Maintenance UPS-sets BIT-2C
- 28-05-24Maintenance UPS sets BIT-1
- 22-05-24Maintenance UPS sets BIT-2A
- 16-05-24Periodic maintenance powerinfra and transformers BIT-2
- 25-04-24Periodic maintenance cooling system BIT-2BCD
- 22-04-24Periodic maintenance cooling system BIT-2A
- 18-04-24Maintenance diesel tanks power generators BIT-2A
- 15-04-24Periodic maintenance cooling system BIT-1
Network maintenance BIT-2A & BIT-2C
Affected services:
- Customers with a network connection to switch "leaf-sw7.bit-2a"
- Customers with a network connection to switch "leaf-sw8.bit-2a"
- Customers with a network connection to switch "leaf-sw1.bit-2c"
- Customers with a network connection to switch "leaf-sw2.bit-2c"
- Customers with a network connection to switch "leaf-sw3.bit-2c"
- Customers with a network connection to switch "leaf-sw4.bit-2c"
Expected impact:
- Disruption of the network connection for approximately 30 minutes during the reboot of the switch
Customer intervention required: No
Reference number: 187579
Summary:
Software of leaf-sw7.bit-2a, leaf-sw8.bit-2a and all four leaf-switches in BIT-2C will be updated.
Details:
The switches will be updated one by one. Due to the update the switches will require a reboot. Customers connected to these switches are expected to have their connection disrupted for approximately 30 minutes.
You can find out which switch you are connected to by checking your invoice or the network statistics in the customer portal.