- 20-02-25Periodic maintenance generatorswitch and transformerswitch BIT-2A
- 19-02-25Maintenance building management system
- 12-02-25Cancelled: Maintenance core routers BIT-1 and BIT-2A
- 12-02-25Emergency maintenance DWDM equipment in Interxion AMS9
- 05-02-25Emergency maintenance MySQL 8 server
- 05-02-25Periodic maintenance fire detection and suppression system BIT-1
- 04-02-25Maintenance various services
- 13-01-25Periodic maintenance power generators BIT-2A
- 13-01-25Periodic maintenance power generators BIT-2BCD
- 13-01-25Periodic maintenance power generator BIT-1
Maintenance diesel tanks power generators BIT-2A
04-04-2024 07:00:00
- 04-04-2024 17:00:00
Urgency: Planned
Affected services:
- emergency power supplies BIT-2A
Expected impact: No redundancy in power generators
Customer intervention required: No
Reference number: 189667
Summary:
The diesel tanks will be replaced by temporary diesel tanks.
Details:
The diesel tanks for the two power generators of BIT-2A need to be certified. Certification can not happen on site therefore our supplier will take the tanks with them and will place temporary diesel tanks in there place.
During this maintenance, one power generator instead of two will be available at all times. In case of a utility power failure, this generator will provide enough power for BIT-2A.
This maintenance will be supervised by BIT engineers.
Affected services:
- emergency power supplies BIT-2A
Expected impact: No redundancy in power generators
Customer intervention required: No
Reference number: 189667
Summary:
The diesel tanks will be replaced by temporary diesel tanks.
Details:
The diesel tanks for the two power generators of BIT-2A need to be certified. Certification can not happen on site therefore our supplier will take the tanks with them and will place temporary diesel tanks in there place.
During this maintenance, one power generator instead of two will be available at all times. In case of a utility power failure, this generator will provide enough power for BIT-2A.
This maintenance will be supervised by BIT engineers.