- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
- 10-01-24BIT en partners zetten de koers voor een gedecentraliseerde Europese cloud met ECOFED-project
- 02-01-24Onze eigen stroom inkopen: de resultaten van 2023
- 24-11-23BIT Friday 2023
Disruption fiber BIT-1 - Equinix AM7
21-06-2018 00:00:00
- 21-06-2018 08:00:00
Urgency: planned
Affected services:
Referencenumber: 155459
Summary:
Our fiber provider needs to move the fiber connection between BIT-1 and Equinix AM7 due to drilling and ground works. The fiber will be cut, moved and then reconnected. Traffic between the BIT network and the internet using this specific link will be moved automatically to alternative paths.
Details:
Our fiber provider received notice from authorities that ground works and drilling will commence shortly. This puts the fiber in its current location at high risk of being damaged.
Update placed at 21/06/2018, 7:05
This maintenance was completed successfully at 5.06h. The fiber was disrupted between 0.35h and 1.33h.
Affected services:
- customer wavelengths between BIT-1 and Equinix AM7
- traffic between BIT network and the internet
- outage for several hours for customer wavelengths
- possible short disruptions for traffic to and from the internet
Referencenumber: 155459
Summary:
Our fiber provider needs to move the fiber connection between BIT-1 and Equinix AM7 due to drilling and ground works. The fiber will be cut, moved and then reconnected. Traffic between the BIT network and the internet using this specific link will be moved automatically to alternative paths.
Details:
Our fiber provider received notice from authorities that ground works and drilling will commence shortly. This puts the fiber in its current location at high risk of being damaged.
Update placed at 21/06/2018, 7:05
This maintenance was completed successfully at 5.06h. The fiber was disrupted between 0.35h and 1.33h.