- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
- 10-01-24BIT en partners zetten de koers voor een gedecentraliseerde Europese cloud met ECOFED-project
- 02-01-24Onze eigen stroom inkopen: de resultaten van 2023
- 24-11-23BIT Friday 2023
Maintenance UPS-sets BIT-2D
13-09-2018 08:00:00
- 13-09-2018 17:30:00
Urgency: Planned
Affected services: Customers with equipment in BIT-2D
Expected Impact: None
Customer intervention required: No
Referencenumber: 153642
Summary:
On Wednesday September 12th and Thursday September 13th between 8.00h and 17.30h our UPS-set supplier will be performing maintenance on our UPS-sets in BIT-2D.
Details:
During the maintenance our batteries will be receiving the BACS management system. This system will continuously monitor the state of all the individual batteries. This system will also equalize the voltage over the batteries.
During this maintenance we will disconnect parts of the batteries from the corresponding UPS-set, each part will be brought back online before a next part will be disconnected. At all times, the remaining capacity in the UPS-set will be ample to retain the normal function of the UPS-set.
Affected services: Customers with equipment in BIT-2D
Expected Impact: None
Customer intervention required: No
Referencenumber: 153642
Summary:
On Wednesday September 12th and Thursday September 13th between 8.00h and 17.30h our UPS-set supplier will be performing maintenance on our UPS-sets in BIT-2D.
Details:
During the maintenance our batteries will be receiving the BACS management system. This system will continuously monitor the state of all the individual batteries. This system will also equalize the voltage over the batteries.
During this maintenance we will disconnect parts of the batteries from the corresponding UPS-set, each part will be brought back online before a next part will be disconnected. At all times, the remaining capacity in the UPS-set will be ample to retain the normal function of the UPS-set.