- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
- 10-01-24BIT en partners zetten de koers voor een gedecentraliseerde Europese cloud met ECOFED-project
- 02-01-24Onze eigen stroom inkopen: de resultaten van 2023
- 24-11-23BIT Friday 2023
Power supply maintenance
08-03-2019 00:00:20
- 08-03-2019 07:00:20
Urgency: planned
Affected services:
- All leaf switches in BIT-2A.
- All leaf switches in BIT-2B.
- Two ring switches in BII-2A and bit-2B.
Expected Impact: None
Customer intervention required: No
Reference number: 161113
Summary:
On Friday March 8th between 0.00h and 7.00h we will perform maintenance on the power supply for various network switches. During this maintance we will migrate the power supply one by one.
Details:
For all leaf switches in BIT-2A and BIT-2B and two ring switches in BIT-2A and BIT-2B we will migrate the power supply to a different feed. All switches have redundant power supply. During this maintenance each switch and each power supply will be moved one by one. During this change the switch will be powered by one power supply for a couple of seconds.
Affected services:
- All leaf switches in BIT-2A.
- All leaf switches in BIT-2B.
- Two ring switches in BII-2A and bit-2B.
Expected Impact: None
Customer intervention required: No
Reference number: 161113
Summary:
On Friday March 8th between 0.00h and 7.00h we will perform maintenance on the power supply for various network switches. During this maintance we will migrate the power supply one by one.
Details:
For all leaf switches in BIT-2A and BIT-2B and two ring switches in BIT-2A and BIT-2B we will migrate the power supply to a different feed. All switches have redundant power supply. During this maintenance each switch and each power supply will be moved one by one. During this change the switch will be powered by one power supply for a couple of seconds.