- 24-04-24Status.bit.nl in nieuw jasje!
- 12-04-24Nieuw bij BIT: GPU hosting
- 25-03-24BIT breidt netwerkconnectiviteit uit met aansluiting op NL-ix^2
- 13-03-24No More Leaks: Samenwerken tegen cybercriminaliteit
- 03-03-24Geen verandering twee jaar na invoering sancties tegen Russische media: FOIC roept (wederom) op tot einde van ondemocratische censuur
- 29-01-24Onzichtbare upgrades
- 16-01-24BIT's Wido Potters wint Felipe Rodriquez Award voor inzet voor privacy
- 10-01-24BIT en partners zetten de koers voor een gedecentraliseerde Europese cloud met ECOFED-project
- 02-01-24Onze eigen stroom inkopen: de resultaten van 2023
- 24-11-23BIT Friday 2023
Maintenance diesel tanks power generators BIT-2A
28-03-2019 07:00:00
- 28-03-2019 12:00:00
Urgency: Planned
Affected services: Emergency power supplies BIT-2A
Expected Impact: No redundancy power generators
Customer intervention required: No
Referencenumber: 161462
Contact: +31 (0)318 648 688, support@bit.nl
Summary:
The diesel tanks will be replaced by temporary diesel tanks.
Details:
The diesel tanks for the two power generators of BIT-2A need to be certified. Certification can not happen on site therefore our supplier will take the tanks with them and temporary diesel tanks are used instead.
During this maintenance, one power generator instead of two will be available at all times. In case of a utility power failure, this generator will provide enough power for BIT-2A.
Affected services: Emergency power supplies BIT-2A
Expected Impact: No redundancy power generators
Customer intervention required: No
Referencenumber: 161462
Contact: +31 (0)318 648 688, support@bit.nl
Summary:
The diesel tanks will be replaced by temporary diesel tanks.
Details:
The diesel tanks for the two power generators of BIT-2A need to be certified. Certification can not happen on site therefore our supplier will take the tanks with them and temporary diesel tanks are used instead.
During this maintenance, one power generator instead of two will be available at all times. In case of a utility power failure, this generator will provide enough power for BIT-2A.